Ask a site manager why the change order log is empty and you’ll get the same answer. The foreman was run off his feet, the GC’s man was in a hurry, and by the time the crew knocked off nobody could remember the details anyway. That empty log costs real money, and the cause is usually timing, not laziness. The paperwork was never going to happen at 5pm from the back of a van.
Why the extra never gets logged
A foreman is judged on keeping the job moving, not on filling in forms. When the GC asks for an extra at half past three, the foreman’s instinct is to say yes, sort the details later, and get the crew back to work. Later never comes. The extra gets done, the job moves on, and by Friday the conversation exists only in one tired person’s memory.
It’s not that foremen don’t care about the money. They do. It’s that the system asks them to do the hardest part of the job at the worst time of day, with the least useful tool. A blank sheet of paper and a pen at knock-off time is a system designed to fail.
Catch it at the moment it happens
The only moment that works is the moment the GC asks. The request is fresh, the work is in front of you, and the person who can approve it is standing there. Two minutes at half past three beats forty-five minutes of reconstruction on Friday, and it gets you a signature from someone who actually remembers saying yes.
Make the capture fit in two minutes
If the process feels like paperwork, your crew will find ways to avoid it. If it feels like taking a photo and a note, they’ll do it without thinking. Keep the capture to four things and no more:
- The job and the location. Two seconds to write, or pick from a list.
- One line on the scope. What’s being asked and why it isn’t in the contract.
- Two photos. One wide shot, one close-up.
- An estimate or a rate. Hours and materials, or an agreed daywork rate.
That’s it. Nothing longer than a text message. If it takes more than a couple of minutes, you’ll be back to empty logs by the end of the month.
Give the foreman the authority to get a signature
The other reason extras don’t get captured is that the foreman doesn’t feel able to price them. He’s not an estimator, and he’s not going to name a number in front of the GC in case he’s wrong. You can fix that without turning him into a commercial manager.
Give him a simple rule. If he can price it, he prices it and gets the signature. If he can’t, he records the instruction, takes the photos and writes “to be priced at daywork or agreed rates” on it, and the office does the number the same day. Either way, the record exists before the crew leaves.
Make the office the backstop
The office has one job the day an extra lands. Turn the capture into a proper change order request and get it to the GC and your own billing before close of play. When the foreman sees that his two-minute note turned into a signed document that ended up in front of the GC’s commercial team, he’ll keep doing it. When nothing happens with his notes, he stops.
Review the misses once a week
Once a week, look at the extras that didn’t make it. Not to blame anyone. To find the pattern. Is it the same GC every time? The same time of day? The same type of work? The answer tells you where the process is breaking, and it’s usually one small fix away from working.
Frequently asked questions
Won’t the GC’s site manager find it confrontational?+
Usually not, if the foreman does it as a matter of course rather than making a point. A site manager who asks for extras knows they’re extras. The ones who get difficult are rare, and they’re the ones you want the paper trail on.
Our foremen are self-employed. How do we get them to do this?+
Make it worth their while and make it easy. If they’re paid for extras by the hour or on daywork, the record is what proves their time. Show them that a signed sheet means they actually get paid for those extra hours, and it stops being your paperwork and becomes their money.
What if the GC asks for extras verbally and never signs anything?+
Record it anyway, the same day, with a photo and an email. A GC who won’t sign isn’t a reason to skip the capture. It’s the exact reason to do it, because that record is what you’ll both be looking at in six months.
We’ve tried forms before. Why would this be different?+
Because the change isn’t a better form. It’s a shorter one, captured at the right moment, with the signature agreed before the crew moves on. If the process takes two minutes, happens on the spot and ends with the GC’s own signature, it doesn’t feel like homework, and that’s why people actually do it.
Empty change order logs aren’t a foreman problem. They’re a process problem, and the fix is to capture extras where they happen, in two minutes, with the authority to get a signature and an office that follows through the same day. Get that loop working and the extras you already do stop leaking away.